Year of 2016

 

INVESTOR: AGROPOLYCHIM AD

PROJECT: “INSTALLATION FOR STEAM PRODUCTION on the production site of AGROPOLYCHIM AD, plots of land 35, 120, 121, 122, 123, 124, 125 and 126”, in the city of Devnya

ACTIVITY: MANUFACTURE, DELIVERY AND INSTALLATION OF THE STEEL STRUCTURE OF A STEAM BOILER PLANT

 

INVESTOR: AURUBIS BULGARIA

PROJECT: Capital repairs: “Ash transportation from an anode converter unit and a melting kiln”, town of Pirdop

ACTIVITY: REPAIR OF REDLERS

 

INVESTOR: CA.S.T.IM. 2000 s.r.l.I—Italy

PROJECT: “STEAM-ELECTRIC POWER STATION”

ACTIVITY: MANUFACTURE OF SUPPORTS AND TENSION BARS FOR STEAM PIPELINES

 

INVESTOR: AGROPOLYCHIM AD

PROJECT: “REPLACEMENT OF A LIFTING HOIST INSTALLATION IN THE PHOSPHORIC ACID WORKSHOP OF AGROPOLYCHIM AD”, city of Devnya

ACTIVITY: MANUFACTURE, DELIVERY AND INSTALLATION OF A METAL STRUCTURE FOR THE REPLACEMENT OF A TELFER INSTALLATION

 

INVESTOR: TRIDENT FREIGHT LTD

PROJECT: “WAREHOUSE FOR PACKING OF INDUSTRIAL PRODUCTS, REPRESENTING AN ALTERATION OF THE INTENDED PURPOSE AND REORGANIZATION OF STAGE IV”—SILOS PARK, city of Devnya

ACTIVITY: MANUFACTURE, DELIVERY AND INSTALLATION OF A METAL STRUCTURE

Year of 2015

 

INVESTOR: BIOCOMPOST BG OOD

PROJECT: ”INSTALLATION FOR COMPOSTING OF ANIMAL WASTE”, village of Karamanovo, PPK START-93

ACTIVITY: MANUFACTURE, DELIVERY, ASSEMBLY AND EQUIPMENT OF AN INSTALLATION FOR THE COMPOSTING OF ANIMAL WASTE

INVESTOR: MEDICOM OOD

PROJECT: “AUTOMOBILE CENTER, WORKING HALL, WAREHOUSE AND INDUSTRIAL GOODS STORE”, city of Ruse

ACTIVITY: MANUFACTURE, DELIVERY AND ASSEMBLY OF A METAL STRUCTURE